New Detached ADU in Tamiami, FL: What It Takes and What It Costs
A new detached ADU in Tamiami, FL typically runs $106,200 to $259,600 for a full standalone structure with its own foundation, utility connections, kitchen, and bath. Design, permitting, and site work usually add 4 to 9 months before the first concrete pour, and construction runs another 6 to 10 months. We’re Groundwork Construction Co., and we build these from foundation to finish line, under the 730-Day Done Right Promise. Call (844) 834-8961 to schedule a free on-site estimate.
How we build a new detached ADU in Tamiami, stage by stage
Every job starts with a survey of what’s actually underground. In Tamiami, that’s rarely a formality.
- Stage 1 – Site visit and feasibility check (1 to 2 weeks). We pull the lot survey, confirm setbacks against your zoning, and look at drainage, existing utilities, and the tree canopy. You decide the footprint and where the structure sits relative to the main house, the fence line, and any future pool or paver work. On most Tamiami lots, the placement question is really a drainage question, and we answer it here rather than after excavation.
- Stage 2 – Design and permit submission (6 to 12 weeks). Architectural drawings, engineered foundation and wind-load plans, and the MEP sheets go out as one package. You sign off on layout, ceiling height, and whether the unit is studio or one-bedroom. Miami-Dade review is thorough on structural and storm-water, so we build review time into the schedule instead of watching it eat the calendar.
- Stage 3 – Site prep and foundation (3 to 5 weeks). This is where Tamiami jobs diverge from the rest of the county. High water tables mean we often dewater the excavation and pour an engineered slab or stem-wall on structural fill. The soil itself gets assessed, because the property’s farming history can flag arsenic on some lots. You decide on utility trench routing to the main house, and we handle the inspection scheduling.
- Stage 4 – Framing through drywall (8 to 12 weeks). Block and frame go up, the roof is dried in, and rough plumbing, electrical, and mechanical are inspected in sequence before insulation. You’ll pick the roof material and window package at the start of this stage so orders land before the crew needs them.
- Stage 5 – Finishes, punch list, and final inspection (5 to 8 weeks). Cabinets, counters, flooring, fixtures, and paint go in. Then we walk the unit with you, correct anything on the punch list, and hold the final inspection. The 730-Day Done Right Promise begins on completion, and if something isn’t right, we make it right.
Styles & brands we work with
- Kitchen remodeling
- Bathroom remodeling
- Home additions & ADU
- Roofing
- Windows & doors
- Driveway & pavers
- Fence
The options you’ll choose between on a detached ADU
Most of the price swing comes down to five decisions. Here’s how they break down honestly.
- Footprint and bedroom count. A 500 to 650 square foot studio comes in at the low end. A one-bedroom at 750 to 900 square feet with a full kitchen pushes toward the top. Every square foot past 700 adds real cost, roughly the same cost per foot you’d spend on a mid-grade addition, but you don’t get the economy of scale you might expect.
- Foundation and site work. A straightforward engineered slab is one number. A slab with dewatering, structural fill, or soil remediation on a lot with a legacy agricultural history is another. We quote the site work separately and show you what drives it, so the number you see is the number you pay.
- Roof and glazing. Shingle with hurricane straps, tile, or metal all meet wind-load requirements here, but they age differently under year-round humidity. Impact windows and doors are the honest choice for a Tamiami structure, and we can specify Andersen or Pella depending on your budget. Cheap glazing is the single biggest regret we see on resale.
- Kitchen and bath level. A simple galley with stock cabinets works for rental use. KraftMaid or Cambria-grade finishes suit a family member’s long-term home. Both are covered by the same workmanship guarantee.
- Utilities and service. A studio can often tie into the main house’s panel with an added meter and subpanel. A full unit with its own HVAC, water heater, and laundry needs its own service, and that adds cost. Separate metering is often worth it if you plan to rent the unit out.
What a new detached ADU costs in Tamiami, FL

Tamiami ADU construction ranges from $106,200 to $259,600 for a fully finished, permitted unit. The low end covers a 500 square foot studio with simple finishes and shared utility service. The high end covers a 900+ square foot one-bedroom with premium finishes, separate metering, and complex site work.
Four variables push the number up or down:
- Size: every 100 square feet adds a meaningful step up in cost, so footprint is the biggest lever.
- Site condition: dewatering, fill, or soil handling can add a substantial share to the base price.
- Utility distance: the farther the ADU sits from the main house, the more trenching, conduit, and pipe you pay for.
- Finish grade: stock versus spec-grade cabinets, countertops, and flooring can swing the total by tens of thousands.
A written estimate from us itemizes each line: site work, foundation, framing, roof, glazing, rough trades, finishes, permits, and inspections. What it doesn’t include is landscaping restoration, pool work, or fence installation unless you ask us to price it. This unit is one part of the wider scope you can see on our Home Additions & ADU in Tamiami page. Our Home Additions & ADU service covers the full range of structures we build. Estimates are free, and financing at 0% for 18 months is available, plus $1,000 off any project over $10,000.
See the difference
Before
After
Before
After
Before
AfterWhat Tamiami homes and land do to this job
Tamiami sits at the western edge of urban Miami-Dade, where the dense subdivisions off SW 8th St back up to the Everglades buffer. That adjacency matters for a detached ADU more than for almost any other project. Builders here work against the county’s strictest floodplain and stormwater rules, and the high water table and sandy limestone soil mean even a modest unit may need dewatering and an engineered foundation. A few miles inland, those steps would be overkill. On lots with a former tomato-farming past, excavation can turn up arsenic-laden soil that triggers special handling. The 33184 ZIP’s 1960s through 1990s concrete block homes often sit close to their lot lines, so footprint placement is tight. Our Tamiami service area covers the whole corridor. Homeowners often pair an ADU with new hardscape, and our Paver Driveways in Tamiami and Concrete Driveways & Concrete Work in Tamiami teams handle the access path and parking pad while the ADU crew is still on site.
Serving Tamiami, FL – Our Local Coverage Area
We serve Tamiami and nearby communities. Use the map below to see the area we cover. If you’re nearby, we can almost certainly help.
Frequently asked about new detached ADU in Tamiami

Most Tamiami projects take 10 to 19 months from signed contract to final inspection, with permitting usually the longest single phase. Construction itself runs 6 to 10 months once the foundation is in. Call us for a realistic schedule for your lot, since permitting timelines shift.
Yes, every detached ADU in Miami-Dade County requires a full building permit, including structural, electrical, plumbing, and mechanical review. We pull the permits and schedule the inspections. You don’t handle the paperwork, and we don’t hand over the keys until the final inspection is passed.
The number climbs when you combine a larger footprint, separate utility metering, premium finishes, and complex site work on a high water table lot. Reach that combination in Tamiami and you’re at the top of the $106,200 to $259,600 range. Call (844) 834-8961 for an exact line-item quote.
No, once we’ve signed off and the scope is fixed, the number you see is the number you pay. The exceptions are genuine surprises hidden under the soil, such as unexpected contamination or undocumented utilities, and we don’t proceed on those without written approval. That’s the upfront pricing our 730-Day Done Right Promise is built around.
Every scratch-built ADU we deliver is covered by the 730-Day Done Right Promise, which starts when the unit is complete. If something we installed isn’t right, we return and correct it. Manufacturer warranties on roof, windows, and appliances pass directly to you.
Get a free estimate on your new detached ADU in Tamiami
Call (844) 834-8961 and a live person answers any hour, any day. We’ll set up a free on-site estimate, walk your lot, talk through footprint and site conditions, and leave you with a written line-item quote. No pressure, no surprise add-ons. If your plan also includes hardscape or other work, homeowners often bundle that with the ADU quote.