Garage Conversion ADU in Palmetto Estates: What It Takes and What It Costs
A garage conversion ADU in Palmetto Estates typically runs $45,000 – $130,000 and takes three to five months from permit pull to final inspection, depending on how much plumbing and electrical you’re moving. Most of that range is driven by whether the existing slab, walls and service panel can carry a living space or need upgrading to Miami-Dade’s hurricane-zone standards. Call (844) 834-8961 for a free on-site estimate and a written, line-item quote before anything is ordered.
How a Garage Conversion ADU Comes Together, Stage by Stage

A garage is built to hold a car, not a person, so the first days on site are about finding out what you actually own before anyone frames a wall. Here’s the sequence we run, and where you make decisions along the way.
Stage 1: Feasibility and permit set (1 – 3 weeks)
We measure the slab, check the ceiling height, photograph the electrical panel and trace the plumbing, then map out where the sleeping area, bath and kitchenette go. This is where you decide whether the unit is a studio or one-bedroom and whether it gets a full kitchen or a kitchenette. Your answers change the permit drawings, so nothing gets submitted until you sign off. Plans go to Miami-Dade County for review; that review, not the build, is usually the longest wait.
Stage 2: Demolition and structural prep (3 – 5 days)
The garage door comes out, the opening gets framed and sealed, and we strip anything that isn’t load-bearing. If the slab has settled or cracked, we level it or pour a thin topping before flooring. You’ll choose at this stage whether to keep the driveway approach as parking or convert it to a patio or outdoor path.
Stage 3: Rough-in trades (2 – 4 weeks)
Plumbing, electrical and HVAC go in after the framing and before the walls close. This is the stage that most often pushes a job to the high end of the range, because running a new drain line to the sewer main and upgrading an older service panel are the two costliest surprises in this work. A pre-drywall inspection has to pass before insulation and drywall go up.
Stage 4: Insulation, drywall and finishes (4 – 6 weeks)
Walls close, then flooring, cabinetry, tile and paint follow. You’ll pick finishes during this window: flooring type, cabinet fronts, countertop material and fixtures. This is where a Caesarstone or quartz counter and a compact Kohler or Moen fixture package can be spec’d to the budget you set at the start.
Stage 5: Final inspections and punch list (1 – 2 weeks)
The county signs off on the mechanical, electrical, plumbing and building permits, then we walk the unit with you and close out the punch list. Every project is covered by our 730-Day Done Right Promise, so if something isn’t right after you move a tenant or family member in, we make it right.
Styles & brands we work with
- Kitchen remodeling
- Bathroom remodeling
- Home additions & ADU
- Roofing
- Windows & doors
- Driveway & pavers
- Fence
The Choices That Shape Your Garage Conversion ADU
Most of the dollars live in four or five decisions. Here’s the honest trade-off on each.
- Slab and ceiling height. A standard 7-to-8-foot garage ceiling feels tight for living space. Raising the ceiling costs more and needs engineering, but it’s the difference between a cramped room and a real one. Keep the existing height and the savings are real, but plan for a smaller footprint or a lower-profile lighting and HVAC layout.
- Plumbing location. A bath tucked against the existing house wall, nearest the main drain, is the cheapest path. Push a bath to the far corner and you’re cutting concrete and running new drain, which adds thousands. Choose your bath location before plans are drawn.
- Electrical service. Many 1960s – 70s Palmetto Estates homes still carry original or undersized panels. If yours won’t support the added load, a service upgrade is required and gets priced into the job. Better to know on day one than mid-build.
- Impact glazing. New windows, doors and the sealed garage opening must meet High-Velocity Hurricane Zone (HVHZ) product approval. Impact-rated units cost more up front but eliminate shutters and satisfy insurance inspections.
- Flooring. Luxury vinyl plank over the slab is fast and moisture-tolerant. Tile is durable and cool underfoot but costs more and takes longer. Wood-look is best kept off a garage slab unless you’re adding a moisture barrier.
What a Garage Conversion ADU Costs in Palmetto Estates, FL

Expect $45,000 – $130,000, with the low end for a straightforward studio that keeps the existing slab, bath location and electrical service. The high end is a one-bedroom with a full kitchen, a service upgrade, new impact glazing throughout and finish-grade cabinetry and stone counters.
Five variables move the number the most: the size and layout you choose; the condition of the slab, walls and roof over the garage; whether plumbing, electrical or structure has to be relocated or upgraded; the finish grade you pick for cabinets, counters and fixtures; and the permit scope, including whether you’re tying a re-roof or hurricane hardening into the same inspection cycle.
A written Groundwork estimate lists every line, from demolition and framing through finishes and final inspections, with permits and inspections included. Upfront pricing, no surprises means the number you see is the number you pay, with no change orders for work already described. What a quote typically doesn’t include: landscaping or irrigation beyond what the unit needs, furnishing or appliances you choose to add later, and any structural repair a slab or wall reveals only after demolition. Ask those questions before you sign.
See the difference
Before
After
Before
After
Before
AfterWhat Palmetto Estates Homes Specifically Do to This Job
Palmetto Estates is an unincorporated, built-out 1960s – 70s suburb of southern Miami-Dade, so this isn’t new construction. It’s renovation and rebuild work on aging concrete-block homes with low-pitch roofs, and every job runs through Miami-Dade County’s post-Surfside review and strict High-Velocity Hurricane Zone product approval rules, not a small-town building department. That matters for a garage conversion because the sealed former garage opening, the new windows and doors, and the roof tie-downs all have to carry HVHZ approval stamps.
The other local reality: many homes here still have original aluminum single-pane windows and original electrical service, and the county’s 40-year recertification rarely lands at a convenient time. When it coincides with a conversion, contractors here routinely fold code-upgrade and re-roof items into the same package. If your conversion is part of a full Home Additions & ADU in Palmetto Estates scope, we plan for that overlap from the start. We cover the whole of Palmetto Estates, and homeowners often pair the new unit’s exterior with Concrete Driveways & Concrete Work in Palmetto Estates or refresh the approach with Asphalt Driveways & Resurfacing in Palmetto Estates. You can see the broader work we do under our Home Additions & ADU service.
Serving Palmetto Estates, FL – Our Local Coverage Area
We serve Palmetto Estates and nearby communities. Use the map below to see the area we cover. If you’re nearby, we can almost certainly help.
Frequently Asked – Garage Conversion ADU in Palmetto Estates

Plan on three to five months from permit submission to final inspection, with the county review usually taking a few weeks of that. Build time itself is about eight to twelve weeks for a typical studio or one-bedroom. Call (844) 834-8961 for a schedule based on your actual layout.
Yes. A habitable unit needs building, electrical, plumbing and mechanical permits through Miami-Dade County, plus HVHZ product approval on doors and windows. Unpermitted work surfaces at resale and during the 40-year recertification. We pull the permits and pass the inspections.
Often, yes. If the bath sits against the shared house wall and the panel already carries the load, the job stays near the low end and needs no structural change. Call for a walk-through to find out which path yours is on.
Roughly $45,000 – $130,000, depending on size, finish grade and whether you need a service upgrade or impact glazing. A written, line-item estimate and a free design consult come before any commitment. Get exact pricing with one call.
Every project is covered by our 730-Day Done Right Promise: if it isn’t done right, we make it right. Technicians are background-checked and arrive in uniform, and we stand behind the work in writing. Call (844) 834-8961 to talk it through.
Get a Free Garage Conversion ADU Estimate in Palmetto Estates
Start with a free on-site estimate. We’ll walk the garage, check the slab, panel and plumbing, and talk through studio versus one-bedroom and what the county will require. You’ll get a written, line-item quote with permits and inspections included, and financing options if you need them. Call (844) 834-8961 today.
Written by the team at Groundwork Construction Co.