Free written scope consultation - allowances, timeline, and change-order rules on paper before a single trade is scheduled
Garage Conversion ADU in Westchester: What It Takes and What It Costs
Converting a garage into a livable accessory dwelling in Westchester usually costs $45,000 – $130,000 once plumbing, electrical, insulation, and Miami-Dade permitting are handled properly, and most jobs run 12 to 20 weeks from demolition to final inspection. The biggest swing factors are whether you’re adding a bathroom or kitchenette, whether the slab and walls need structural work, and how many inspections the county layers on. Call (844) 834-8961 for a free on-site estimate before you commit to a scope.
How the Job Runs, Step by Step

Garage conversion ADU work in Westchester rarely follows a straight line, but the sequence below is what we hold our schedule to. At each stage you make one or two decisions, and the crew takes it from there.
Stage 1: Feasibility and design (1 – 2 weeks)
We walk the garage with you, check the slab for cracks or settlement, measure ceiling height, and confirm the electrical panel can carry the added load. This is where you decide the layout: a studio with a single bathroom, or a one-bedroom with a kitchenette. Our team handles the drawings and the Miami-Dade submittal packet, since the permit paperwork (not the framing) is what usually sets the schedule in this market.
Stage 2: Permit approval and site prep (3 – 6 weeks on the county side)
Miami-Dade reviews conversions under the High-Velocity Hurricane Zone rules, so you’ll see product approvals (NOAs) and wind-load documentation bundled into the permit. While the county reviews, we demo interior finishes, clear out stored items, and verify the existing slab and block walls.
Stage 3: Rough-in trades (2 – 3 weeks)
Plumbing, electrical, and HVAC go in next. If you’re adding a bathroom, we trench the slab for the drain line and tie into the main stack, which is the single biggest cost variable on a conversion. Rough inspections happen before any drywall goes up.
Stage 4: Insulation, drywall, and finishes (3 – 5 weeks)
Closed-cell spray foam or rigid board against the block walls, drywall, and your finish selections. This is where you pick flooring, paint, cabinetry, and fixtures. Caesarstone and Kohler are two of the brands we regularly specify for kitchenette and bath finishes.
Stage 5: Final inspections and punch list (1 – 2 weeks)
Miami-Dade signs off on framing, electrical, plumbing, and final occupancy. We walk the space with you, fix anything on the punch list, and hand over the certificate of occupancy.
Styles & brands we work with
- Kitchen remodeling
- Bathroom remodeling
- Home additions & ADU
- Roofing
- Windows & doors
- Driveway & pavers
- Fence
The Choices That Shape Your Conversion
Most of the cost and comfort difference between one garage ADU and another comes down to four decisions. Here’s what we walk you through:
- Flooring over the slab: Polished concrete ($6 – $12/sq ft) is the bulletproof choice in a humid Westchester garage; luxury vinyl plank ($4 – $8) is warmer and cheaper but needs a vapor barrier; porcelain tile ($8 – $15) holds up to moisture but feels cold underfoot.
- Bathroom style: A half-bath keeps plumbing short and cheap; a full bath with a walk-in shower adds $4,500 – $12,000 but makes the unit rentable as a true one-bedroom.
- Kitchenette: A simple sink-and-cooktop setup with a Blanco sink and Moen faucet runs $3,000 – $8,000; a full galley with cabinetry leaps to $12,000+.
- Insulation and AC: Spray foam plus a mini-split ($4,000 – $9,000) beats window units every time in a Miami summer; the mini-split alone justifies its cost in tenant comfort.
- Garage door treatment: Some homeowners keep the door in place disguised as a wall; others frame it in and stucco it over for a cleaner exterior. Framing in is usually the better long-term look but costs more.
What a Garage Conversion ADU Costs in Westchester, FL

The working range for a full garage conversion ADU in Westchester is $45,000 – $130,000, with most completed units landing in the $65,000 – $95,000 band for a one-bedroom with a bath and kitchenette. Here’s what pushes you toward the low or high end.
| Line Item | Typical Range |
|---|---|
| Design and permit package | $3,000 – $8,000 |
| Demolition and site prep | $2,000 – $5,000 |
| Plumbing (bath + kitchenette) | $6,000 – $15,000 |
| Electrical and panel upgrade | $3,500 – $9,000 |
| Insulation, drywall, framing | $7,000 – $18,000 |
| Flooring and finishes | $5,000 – $14,000 |
| HVAC (mini-split or ducted) | $4,000 – $9,000 |
| Kitchenette and bath fixtures | $5,000 – $16,000 |
| Garage door infill or replacement | $2,000 – $7,000 |
The four variables that move the number most: whether plumbing requires slab trenching (adds $4,000 – $9,000), whether the electrical panel has spare capacity (adds $2,500 – $6,000 if a service upgrade is needed), whether you add a full kitchen (vs. a kitchenette), and finish grade. Our written estimate itemizes every one of these; the number you see is the number you pay, covered by our 730-Day Done Right Promise.
See the difference
Before
After
Before
After
Before
AfterWhat Westchester Homes Do to This Job
Almost everything in ZIP 33165 is built-out, post-1950s concrete-block housing under Miami-Dade’s hurricane-zone code, which means a garage conversion here is always a code-upgrade job rather than a simple remodel. The typical garage we open up has a slab that’s held up through 60+ years of Miami heat, block walls that need furring and insulation before drywall, and a single electrical panel that’s already maxed out. We see two recurring problems: undersized overhead doors that leak summer downpours into the space, and termite damage in the furring strips behind stucco. On top of that, the permit-and-NOA process is what controls the calendar – not the framing – so plan around it. Westchester homeowners who also want to tidy up the front of the property often pair this with Asphalt Driveways & Resurfacing in Westchester or Concrete Driveways & Concrete Work in Westchester while the garage is out of use.
If the conversion is part of a wider plan, it fits naturally into the scope of Home Additions & ADU in Westchester. To see the full breadth of what we handle in the area, visit our Home Additions & ADU service page, or read more about coverage across Westchester.
Serving Westchester, FL – Our Local Coverage Area
We serve Westchester and nearby communities. Use the map below to see the area we cover. If you’re nearby, we can almost certainly help.
Frequently Asked – Garage Conversion ADU in Westchester

Plan for 12 to 20 weeks from contract to certificate of occupancy, with 3 to 6 of those weeks spent waiting on Miami-Dade permit review. Call (844) 834-8961 for a timeline mapped to your specific garage.
Yes. Any habitable-space conversion in Miami-Dade County requires a building permit, and because 33165 falls under the High-Velocity Hurricane Zone rules, you’ll need product approvals and wind-load documentation on file. We pull the permits and take inspections through to final sign-off.
Only if you skip the bathroom and kitchenette – which most homeowners don’t want to do, since a unit without them isn’t rentable as a true ADU. Adding even a half-bath means trenching the slab for a drain line. Call us to talk through whether a dry conversion makes sense for your use case.
Expect $45,000 – $130,000 depending on size, plumbing scope, electrical capacity, and finish grade. Our written quotes itemize every line so nothing appears mid-job. Call (844) 834-8961 for an exact quote – the on-site estimate is free.
Every conversion we complete is covered by our 730-Day Done Right Promise on workmanship, and manufacturer warranties pass through on fixtures and systems. If something isn’t right, we come back and make it right.
Ready to Plan Your Westchester Garage Conversion ADU?
Call (844) 834-8961 to schedule a free on-site estimate for your garage conversion ADU in Westchester. A live person answers around the clock, and we’ll walk the garage with you, check the slab and panel, and hand you a written itemized quote with no surprises. Bring your questions about layout and budget – we’ll give you straight answers on what the job really takes and what it will really cost.
Written by the team at Groundwork Construction Co.