New Detached ADU in Westwood Lakes, FL: What the Job Actually Involves
A new detached ADU in Westwood Lakes usually runs $45,000 – $130,000 and takes four to six months from signed estimate to final inspection, with the county permit and plan-review cycle eating a large share of that clock. You’re building a separate, self-contained living structure in the side yard or back lot of a mid-century ranch: foundation, framing, roof, utility tie-ins, and its own kitchen and bath. Call (844) 834-8961 and we’ll schedule a free on-site walkthrough to talk through lot size, setbacks, and budget.
How we build a detached ADU here, stage by stage

The sequence isn’t glamorous, but knowing the order helps you plan your decisions. Here’s what actually happens.
Stage 1 – Site review and feasibility (week 1). We walk the lot with you and check setbacks, easements, drainage, and how utilities reach the footprint. On a Westwood Lakes ranch lot, the wet corner and the existing septic or sewer tap location decide a lot of the layout before anything else does. You decide the rough placement and size at this stage.
Stage 2 – Design, engineering, and permit (weeks 2 – 10). Drawings go to an engineer for wind-load and structural calcs, then to Miami-Dade County for plan review. This is the longest stretch and the one that surprises people. You approve final plans and finish schedules here. Nothing gets poured until the permit is issued and the inspections are scheduled.
Stage 3 – Site prep and foundation (weeks 10 – 13). Clearing, grading, form work, and the slab or stem-wall foundation. Concrete goes in and cures. You’ll pick exterior door and window models now, because lead times on impact-rated units are long.
Stage 4 – Framing, roof, and rough-in (weeks 13 – 20). Wall framing, roof structure, then rough electrical, plumbing, and mechanical, each inspected before the walls close. This is where the utility trench tie-ins happen.
Stage 5 – Finishes, trim, and final inspection (weeks 20 – 26). Insulation, drywall, cabinets, flooring, fixtures, paint, and the final county inspection and certificate of occupancy. You make your cosmetic choices (cabinet color, flooring, tile) at the start of this stage so nothing sits waiting.
Styles & brands we work with
- Kitchen remodeling
- Bathroom remodeling
- Home additions & ADU
- Roofing
- Windows & doors
- Driveway & pavers
- Fence
The options you’ll actually choose between
Most of the money sits in a handful of decisions. Here’s the honest trade-off on each.
- Slab-on-grade vs. stem-wall foundation. Slab is faster and cheaper; a raised stem wall handles the flat Miami-Dade lot better if drainage is marginal and keeps the floor out of standing water after a heavy rain.
- Stick-frame vs. modular panelized build. Panelized systems like Dvele can shorten on-site framing time, but you’re fitting a factory footprint onto a tight lot, so confirm access for delivery. Stick-frame gives you more freedom in shape and matches the ranch architecture next door.
- Impact-rated glazing. This isn’t optional in Miami-Dade. The choice is between brands and styles, not whether. Budget for it up front rather than discovering it at final inspection.
- Kitchen and bath finish grade. A prefab cabinet line keeps the budget in check; a semi-custom line (think KraftMaid) adds cost but holds up better and lifts resale. Tile vs. luxury vinyl plank on the floor is a real durability call in this humidity.
- Utility strategy. Tying into the main house’s panel and water line is cheaper than a separate meter and service, but only if the main service has capacity. If it’s already maxed, a separate drop is the cleaner path.
You can spec Sakrete bagged concrete for small pads and footings; structural pours come from a ready-mix supplier. We’ll walk you through each line so the numbers mean something.
What a New Detached ADU costs in Westwood Lakes, FL

Plan on $45,000 – $130,000 for a detached ADU here, with most Westwood Lakes projects landing in the middle of that band. The low end is a compact, simple-roofed studio of a few hundred square feet with basic finishes; the high end is a larger one- or two-bedroom unit with a full kitchen, upgraded finishes, and a separate utility service.
What moves the number:
- Size and configuration – square footage is the single biggest driver; each added bedroom and bath adds cost.
- Existing utility condition – if the main house’s panel or water service is near capacity, upgrading it is a real line item.
- Site conditions and access – a tight side-yard entry that blocks a concrete truck changes the pour cost.
- Finish grade – cabinets, flooring, and fixtures can swing the total by tens of thousands.
- Permit and inspection scope – Miami-Dade’s post-Surfside review and wind-mitigation requirements add cost that a simpler market wouldn’t carry. Your written estimate itemizes each of these lines, and the number on it is the number you pay.
See the difference
Before
After
Before
After
Before
AfterWhat Westwood Lakes homes specifically do to this job
Westwood Lakes (ZIP 33165) is a built-out, unincorporated pocket of Miami-Dade, which means nearly every project here is an addition or rebuild on a 1960s – 70s concrete-block ranch, not new development. That changes the job in concrete ways. The original single-story homes often have limited electrical panel capacity and aging plumbing, so the first thing we check is whether the main service can carry a second dwelling – and frequently it can’t without an upgrade. Every structure has to clear Miami-Dade’s post-Surfside recertification, wind-mitigation, and permitting regime, so the ADU plans need engineered wind-load calcs and product-approval (NOA) paperwork for the impact glazing. And because South Florida’s hurricane season and year-round humidity shape everything, we’re detailing moisture barriers and roof flashing a northern builder wouldn’t think twice about. In the blocks near the Westwood Lakes park and along the shaded side streets, we see tight lots where setback and drainage decide the footprint before design starts.
Serving Westwood Lakes, FL – Our Local Coverage Area
We serve Westwood Lakes and nearby communities. Use the map below to see the area we cover. If you’re nearby, we can almost certainly help.
Frequently asked – New Detached ADU in Westwood Lakes

Expect four to six months, with plan review and permit approval often taking the longest single block. Call (844) 834-8961 for a schedule mapped to your lot.
Yes – a detached ADU needs full Miami-Dade County permitting, including structural, wind-load, and utility review. We handle the permit and inspection process and stand behind the result.
Usually yes – a detached unit taps into existing water, sewer, and power, so the main house stays intact. The main question is whether the existing service has capacity, which we check during the site review.
$45,000 – $130,000, depending on size, finish grade, and utility upgrades. Call (844) 834-8961 for an exact quote – estimates are free.
Every job is backed by our 730-Day Done Right Promise: if it isn’t done right, we make it right. That covers the workmanship long after the final inspection.
Get a free on-site estimate for your Westwood Lakes ADU
Building a detached ADU is part of a bigger picture for most homeowners here, and it often sits alongside other projects. If you’re planning beyond the ADU itself, our Home Additions & ADU in Westwood Lakes page covers the wider scope, and homeowners often pair this with Concrete Driveways & Concrete Work in Westwood Lakes or Paver Driveways in Westwood Lakes to finish the lot. We serve the whole Westwood Lakes area, and our Home Additions & ADU service line is ready to walk your lot. Call (844) 834-8961 for a free estimate – a live person answers, and on the call we’ll set a time to measure your lot and talk budget.
Written by the team at Groundwork Construction Co.