Free written scope consultation - allowances, timeline, and change-order rules on paper before a single trade is scheduled
Garage Conversion ADU in Richmond Heights, FL: What It Takes and What It Costs
A garage conversion ADU in Richmond Heights typically runs $45,000 – $130,000 and takes 3 to 5 months from permit to final inspection. You’re turning an existing attached or detached garage into a legal, rentable or family-ready living unit – full bath, kitchenette, sleeping area, separate entrance – usually on a lot that’s already built out. Call (844) 834-8961 to schedule a free on-site estimate and we’ll walk your garage with you.
How the Work Actually Unfolds, Stage by Stage

Every Richmond Heights garage conversion we run follows the same sequence. Here’s the honest version, including the parts that slow a job down.
Stage 1: Feasibility and layout (week 1)
We measure the garage, check the slab, and look at where the electrical panel, water heater, and any existing plumbing run. In a 1950s – 70s Richmond Heights home this is the moment we find out whether the garage slab is a monolithic pour or a floating slab – the difference changes your floor assembly. You decide the layout at the end of this stage: where the sleeping area sits, where the kitchenette goes, and whether the unit gets its own exterior door or shares the existing side entrance.
Stage 2: Permit submission and plan review (weeks 1 – 4)
We prepare the drawings and submit to Miami-Dade County. Because Richmond Heights sits inside the High Velocity Hurricane Zone, the plans have to show Miami-Dade NOA-approved products for the doors, windows, and any new roof structure, and the county runs a threshold-inspection sequence on top of the standard inspections. This review period is the single longest thing you don’t control. You’ll sign the permit application and any HOA paperwork during this window.
Stage 3: Demo and shell prep (weeks 4 – 5)
The garage door comes out and gets framed and finished as a wall. We strip drywall, remove the old overhead door track and opener, and cut the slab where plumbing has to go if the unit needs a bath relocated from the existing stack. This is a 5 to 7 day stage on a typical single-car or two-car Richmond Heights garage. You choose the new exterior door configuration before framing closes.
Stage 4: Rough-in trades (weeks 5 – 8)
Plumbing, electrical, and HVAC rough-in happen in sequence, then the county inspects all three before anything gets closed up. This stage is where sliding the bath against an existing wall stack versus running new drain lines across the slab swings your price the most. You’ll pick fixtures – vanity, shower or tub, toilet, water heater type – right before rough-in so the plumbing can be set to fit.
Stage 5: Insulation, drywall, finishes, final inspection (weeks 8 – 16)
Insulation and drywall go up, then floor, cabinets, countertop, paint, trim, and fixtures. Final inspection comes after the punch list is clear. You walk the finished unit with us before we sign off.
Styles & brands we work with
- Kitchen remodeling
- Bathroom remodeling
- Home additions & ADU
- Roofing
- Windows & doors
- Driveway & pavers
- Fence
The Choices That Shape Your Garage Conversion ADU
These are the decisions that move a Richmond Heights garage conversion from a $45,000 box to a $130,000 finished unit. Each one has an honest trade-off.
- Detached versus attached garage. An attached garage shares two or three walls with the house, so you save on exterior sheathing, roofing, and HVAC routing. A detached garage in Richmond Heights has to be tied to the house utilities with trenched lines, which adds cost but gives the ADU its own privacy and separate utilities if you want them.
- Bath and kitchenette plumbing location. Tying the new bath to the existing drain stack is the cheap route. Running a new stack across the slab means breaking concrete, re-pouring, and a longer permit review. That swing alone is often $8,000 – $20,000.
- Exterior door and window package. In the HVHZ, doors and windows must carry a Miami-Dade NOA. Impact-rated glass costs meaningfully more than standard but eliminates shutters and passes the county’s product-approval check on the first review. Barrette and Master Halco make fencing and gate systems homeowners often pair with an ADU side entrance, and the same hurricane-rated thinking applies to the gate hardware.
- Flooring. Engineered luxury vinyl plank ships fast, handles South Florida humidity, and stays in budget. Tile is more durable in a wet unit and matches the existing terrazzo or tile found in many Richmond Heights homes. Site-finished hardwood is a poor fit in a garage slab that may wick moisture.
- HVAC. A dedicated ductless mini-split is the cheapest path and gives the tenant their own thermostat. Tying into the house system with a new zone can be cheaper on equipment but adds labor and complicates the permit.
- Kitchenette grade. A compact sink, two-burner cooktop, and undercounter fridge is sufficient for a legal ADU. A full kitchen with a range hood, 220V circuit, and dishwasher pushes cost higher and needs additional electrical capacity.
What a Garage Conversion ADU Costs in Richmond Heights, FL

Expect $45,000 – $130,000 for a garage conversion ADU in Richmond Heights. Most jobs we quote land in the $60,000 – $95,000 band, and the variables below explain why some jobs run to either end.
| Scope element | Typical range |
|---|---|
| Attached garage, plumbing on existing stack, mid-grade finishes | $45,000 – $70,000 |
| Attached garage, new bath stack, full kitchenette, dedicated HVAC | $70,000 – $100,000 |
| Detached garage, trenched utilities, impact door package, premium finishes | $95,000 – $130,000 |
| Permit, plan review, and impact-fee portion | Included in written quote |
Five things push the number to the high end: whether the garage is detached (trenching and separate utilities), how far the new bathroom plumbing runs from the existing stack, whether the electrical panel has capacity for the additional loads or needs an upgrade, the impact-rated door and window package Miami-Dade requires, and finish grade (cabinets, countertops, flooring). Structural changes – cutting a beam, reinforcing the roof for a flat-ceiling conversion – add cost on top of all of it. A written estimate from us lists each of these line by line, not as one bundled number. Call (844) 834-8961 for an exact quote on your specific garage – estimates are free.
See the difference
Before
After
Before
After
Before
AfterWhat Richmond Heights Homes Specifically Do to This Job
Richmond Heights was built out between the 1950s and 1970s, and much of that housing is single-family CBS – concrete block and stucco – with carports and oversized garages. Because the area is essentially full, almost no garage here is being converted in a new build; we’re renovating garages that have been standing for 50 to 70 years. That means two failure modes show up on nearly every job. First, the carport that was walled in at some point in the 1980s often has no footing under the new walls and no permit on file, and we have to bring that up to code for the ADU to pass final inspection. Second, the original garage slab may sit below the finish-floor elevation of the house, which means the new unit floor needs a raised assembly – a detail we price in upfront, not after demo.
The county permitting reality is where Richmond Heights garage conversions get their timeline from. Miami-Dade’s High Velocity Hurricane Zone rules mean every exterior door, window, and any new tie-down or strap assembly must use Miami-Dade NOA-approved products and pass the county’s threshold-inspection sequence. That rigor is a good thing – it’s why a permitted conversion adds real value – but it does mean plan review usually runs several weeks before a hammer swings. We handle the permit, the NOA product schedules, and every inspection along the way. If your project grows into a broader build, see our Home Additions & ADU in Richmond Heights work, and homeowners converting a detached garage often pair the ADU access with Asphalt Driveways & Resurfacing in Richmond Heights for the new parking and path to the door. Every job is covered by our Home Additions & ADU service and by the 730-Day Done Right Promise. We cover Richmond Heights and the surrounding South Miami-Dade neighborhoods including Kendall, Sunset, The Crossings, and Three Lakes.
Serving Richmond Heights, FL – Our Local Coverage Area
We serve Richmond Heights and nearby communities. Use the map below to see the area we cover. If you’re nearby, we can almost certainly help.
Frequently Asked: Garage Conversion ADU in Richmond Heights

Most Richmond Heights garage conversion ADUs take 3 to 5 months from permit submission to final inspection, with plan review often eating the first several weeks. The construction itself runs 10 to 14 weeks on a typical single-car or two-car garage. Call (844) 834-8961 to get a timeline specific to your property.
Yes. Miami-Dade County requires a permit for any garage conversion to living space, and the work has to meet the county’s High Velocity Hurricane Zone wind-load and product-approval rules. An unpermitted conversion will fail at resale and can’t be legally rented. We pull the permit and manage every inspection.
Often, yes – if the existing garage sits adjacent to a bathroom wall or utility stack, the new bath can tie directly to that drain without breaking the slab. In our experience with Richmond Heights garages built between the 1950s and 1970s, most can save $8,000 – $20,000 by keeping the plumbing where it is. We’ll tell you during the free estimate which route your garage allows.
The range is $45,000 – $130,000, with most jobs landing between $60,000 and $95,000. Whether the garage is detached, how far the new plumbing runs, and the impact-rated door and window package are the biggest swing factors. Call (844) 834-8961 for a written line-item estimate – estimates are free.
Every garage conversion we complete is covered by the 730-Day Done Right Promise – if it’s not done right, we make it right. That’s one of the longer workmanship guarantees in residential construction. The materials we specify come from top-tier partners so the unit holds up in South Florida humidity.
Get Your Free Garage Conversion ADU Estimate in Richmond Heights
We’ll come out, walk the garage, measure the slab, and check the panel and plumbing stack – then hand you a written estimate with line items, not a single round number. Our licensed and insured team answers the phone 24/7 with a live person, and our technicians bring up to 12 years of experience to every job. Call (844) 834-8961 to schedule your free estimate. Concrete Driveways & Concrete Work in Richmond Heights is a natural companion if your conversion adds a parking pad.
Written by the team at Groundwork Construction Co.