Garage Conversion ADU in Sunset, FL: What It Costs and How Long It Takes
A garage conversion ADU in Sunset, FL typically runs $45,000 – $130,000 and takes about 4 to 7 months from permit application to final inspection. The job turns an existing attached or detached garage into a legal, rentable or family-ready living space under one roof: framing the door opening closed, raising or finishing the floor, running new electrical, plumbing and HVAC, and passing Miami-Dade County inspections at each stage. Call (844) 834-8961 for a free on-site estimate and a written line-item scope before you commit to anything.
The Stage-by-Stage Path From Empty Garage to Signed-Off ADU

Most Sunset garages we open up already have a story: a 1960s concrete block shell, a slab that slopes toward the driveway, a single 16-foot overhead door with a legacy torsion spring that hasn’t cycled cleanly in years. Converting it means undoing some of that history before you add a kitchenette. Here’s the real sequence.
Stage 1 – Feasibility and permit set (2 – 4 weeks). Before a single wall moves, we measure the existing envelope, check ceiling height (7 feet 6 inches is the practical floor for a habitable room), and look at how the garage ties into the main house foundation. Because Sunset is unincorporated Miami-Dade, the plans go to Miami-Dade County Building Department, not a city hall, and the review involves zoning, structural, electrical and mechanical reviewers in sequence. You decide here whether the unit is a studio or one-bedroom layout, and whether you want a full kitchen or a kitchenette. That decision drives everything downstream.
Stage 2 – Demolition and shell work (week 1 – 2 of construction). The overhead door and track come out, the driveway apron gets addressed, and we frame and sheath the new wall. The slab gets evaluated. Many Sunset slabs sit below grade and need a vapor barrier and a raised subfloor rather than a direct pour-over, because our summer humidity will find every cold joint. You pick the floor system here: stained concrete if the slab qualifies, engineered wood or tile over a raised assembly if it doesn’t.
Stage 3 – Rough-in (weeks 2 – 5). This is the expensive, invisible phase. Electrical panel capacity gets checked first. A 1950s – 1970s Sunset home may still be on a 100-amp panel, and adding a full ADU with its own HVAC, range and water heater can push past that. If a panel upgrade or a subpanel is needed, you’ll see it in the line item before we start, not after. Plumbing gets trenched to the nearest wet wall or tied into the main house system. HVAC gets sized for the new square footage, not borrowed from the house. Everything here is inspected before it’s closed.
Stage 4 – Insulation, drywall, finishes (weeks 5 – 12). Impact-rated windows and a new exterior door get set. Wall insulation goes in, drywall goes up, and you start choosing the visible stuff: cabinet grade, countertop material, flooring, fixtures, paint. This is where budgets move most, and where we hand you a fixed selection sheet so the number doesn’t drift.
Stage 5 – Final inspections and punch (weeks 12 – 16). Electrical, mechanical, plumbing and building finals. Wind-mitigation product approvals are verified against what was actually installed. Certificate of occupancy gets issued, and the unit is legal to live in or rent. We walk it with you, fix the punch list, and hand over documentation.
Styles & brands we work with
- Kitchen remodeling
- Bathroom remodeling
- Home additions & ADU
- Roofing
- Windows & doors
- Driveway & pavers
- Fence
The Choices That Actually Shape Your ADU
Every garage conversion comes down to a handful of decisions. Here’s what you’re picking between, and the honest trade-off on each.
- Overhead door removal, wall-in vs. keeping the opening as glass. Walling it in with concrete block and stucco matches the house and costs less. A full-height glazed opening looks sharp and brightens the space, but impact glass for an opening that size adds real money and needs product approval for wind load. Most Sunset homeowners wall it in and add two or three impact windows on the side walls.
- Floor assembly. Direct-finish stained concrete is the cheapest option and holds up well if the slab is sound and dry. A raised subfloor with engineered wood or luxury vinyl handles a below-grade slab and feels warmer, but adds $6 – $14 per square foot depending on finish.
- Kitchenette vs. full kitchen. A kitchenette (sink, under-counter fridge, two-burner) keeps plumbing runs short and often avoids a panel upgrade. A full kitchen with a range and full-size fridge usually needs its own circuit and sometimes a subpanel. We spec Sakrete for any concrete patching and slab work, and we source cabinetry through our established brand partners so you’re choosing quality, not whatever’s in stock.
- HVAC: mini-split vs. ducted. A ductless mini-split is simpler to install in a converted garage and cheaper to run for one zone. A ducted system ties into the house and looks cleaner on the wall, but requires ceiling space and more rough-in.
- Bathroom placement. A half bath near an existing wet wall is the least expensive layout. A full bath with a walk-in shower requires relocating the drain and vent, which is where plumbing cost climbs fast.
What Garage Conversion ADU Costs in Sunset, FL

Expect $45,000 – $130,000 for a garage conversion ADU in Sunset, FL, with most finished units landing between $60,000 and $95,000. The low end is a studio with a half bath, a mini-split, retained slab and a walled-in door opening. The high end is a one-bedroom with a full kitchen, a new slab assembly, a panel upgrade, impact glazing and premium finishes.
What moves the number most:
- Panel capacity. If the main house still runs on 100 amps, an upgrade or subpanel can add thousands.
- Slab condition. A dry, level slab saves on floor assembly. A below-grade or cracked slab triggers a vapor barrier, patch work and often a raised floor.
- Plumbing relocation. Tying into a nearby wet wall is cheap. Moving a drain across the slab is not.
- Finish grade. Cabinet, counter and flooring choices swing the total by well over $20,000 between builder-grade and mid-premium.
- Permit scope. Miami-Dade County’s post-Hurricane Andrew wind-mitigation review adds documentation and product-approval steps that a simple renovation doesn’t carry.
Your written estimate should include demolition, permit fees, framing, electrical, plumbing, HVAC, insulation, drywall, windows, doors, finishes and final inspection coordination. It should not assume a panel upgrade, a new slab pour, or termite damage repair unless we’ve seen the condition, so those get flagged as contingencies with a ceiling price, not blank space.
See the difference
Before
After
Before
After
Before
AfterWhat Sunset Homes Specifically Do to This Job
Sunset is unincorporated, and that single fact shapes every garage conversion here. Plans route through Miami-Dade County Building Department, and the review layers are real: zoning, structural, electrical, mechanical. Contractors who work here learn to anticipate the wind-mitigation product-approval piece early, because Miami-Dade’s post-Andrew codes are stricter than what many neighboring municipalities enforce, and a missed approval on a window or door can stall a final inspection for weeks.
The housing stock does the rest. Most Sunset homes are 1950s – 1970s concrete block and stucco single-family houses with flat or low-slope roofs, and many were expanded at some point, so we regularly find a garage that was bumped, walled or re-roofed over the decades. Tying a new ADU into that older structure means checking how the garage roofline actually meets the house before we frame. Our subtropical climate also matters: hot, humid summers and hurricane season drive wind-load requirements, waterproofing detail and mold prevention. A garage that’s been closed up for years often has moisture already working on the bottom plate. We plan outdoor work around the afternoon thunderstorms, and we waterproof the wall-in wall like it’s an exterior wall, because in Sunset it effectively is.
This kind of work is part of a wider Home Additions & ADU in Sunset, and if your project grows into a full scope, that’s where it lives. Homeowners often pair this with Concrete Driveways & Concrete Work in Sunset, since the old apron and parking pad usually need rework once the garage is walled in. Our Home Additions & ADU service covers the full range of build types, and we work across Sunset and the surrounding area.
Serving Sunset, FL – Our Local Coverage Area
We serve Sunset and nearby communities. Use the map below to see the area we cover. If you’re nearby, we can almost certainly help.
Frequently Asked – Garage Conversion ADU in Sunset

Plan on 4 to 7 months total, with roughly 2 to 4 weeks in Miami-Dade County plan review before construction starts. The construction itself usually runs 12 to 16 weeks. Delays usually come from permit review and from anything that turns up in the existing structure, not from the finish work. Call (844) 834-8961 and we’ll give you a realistic schedule for your specific garage.
Yes. Any habitable conversion in unincorporated Miami-Dade County requires a building permit, and the finished unit needs a certificate of occupancy to be legal. Skipping the permit can force you to open walls later and can complicate insurance and resale. We handle plan submission and inspection coordination as part of the job. Call (844) 834-8961 to walk through what your property needs.
Often yes, if the garage shares a wall with the house’s existing plumbing runs and the layout puts the bath near that wall. A studio with a kitchenette and half bath is the easiest to keep structural and plumbing changes minimal. A one-bedroom with a full bath usually needs some relocation. We confirm this during the on-site estimate before you commit to a design.
Most projects land between $45,000 and $130,000, with a typical finished unit around $60,000 to $95,000 depending on layout, finishes and how much existing structure needs rework. Panel capacity and slab condition are the two biggest swing factors. Call (844) 834-8961 for an exact quote – estimates are free and we put everything in writing.
Every garage conversion ADU we build is covered by our 730-Day Done Right Promise – if it’s not done right, we make it right. That covers workmanship for two full years, which is longer than most builders offer. Calls are answered by a live person 24/7, and our technicians are background-checked and arrive in uniform. Call (844) 834-8961 with a warranty question and you’ll get a real answer.
Get a Free Estimate for Your Garage Conversion ADU in Sunset
We come to your property, look at the actual slab, panel, roofline and plumbing wall, and put a line-item written estimate in your hands with no change orders once work starts. You’ll know which choices drive the price and which don’t. Call (844) 834-8961 to schedule your free on-site estimate – a live person answers around the clock, and 0% financing for 18 months is available, plus $1,000 off any project over $10,000.
Written by the team at Groundwork Construction Co.