Garage Conversion ADU in Three Lakes, FL: What It Costs and How Long It Takes
A garage conversion ADU in Three Lakes usually runs $45,000 – $130,000 and takes 4 to 7 months from the first permit submittal to the final inspection. The core of the job is turning an existing garage bay into a legal, wind-rated dwelling: new insulation, drywall, flooring, a bathroom and kitchenette, a separate entry, and a door assembly that’s rated for South Florida wind loads and flood elevation. Call (844) 834-8961 for a free on-site estimate.
How We Run a Garage Conversion ADU From First Cut to Final Inspection

A garage conversion is not a remodel that happens to have a bed in it. It’s an occupancy change, and the sequence matters because the permit and inspection chain runs the whole job. Here’s the order we work in.
Stage 1: Feasibility and permit set (2 to 4 weeks)
Before anyone cuts drywall, we measure the slab, check the existing garage door header and the ceiling height (a garage conversion needs 7 feet of clear finished height in Three Lakes, and older CBS garages sometimes come up short once you add a floor and ceiling finish), and confirm whether the bay sits in a flood zone that triggers elevation requirements. You’ll decide two things here: whether the ADU is a studio or a one-bedroom, and whether you want a full kitchen or a kitchenette. Those two choices move the number by $20,000 or more, so we settle them before drawings go out.
Stage 2: Demolition and structural prep (3 to 5 days)
We pull the existing overhead door and its tracks, remove any non-bearing partitions, and strip the slab to bare concrete. The old garage door opening gets framed and closed to a window-and-entry-door configuration. If the roofline needs a wind-rated connection upgrade where the garage meets the main house, that’s a day of its own. This is also when we check the slab for cracks and moisture, and it’s the stage where a lot of Three Lakes jobs turn up original single-pane openings that fail current wind-load code.
Stage 3: Rough-in trades and framing (2 to 3 weeks)
Plumbing, electrical, and mechanical rough-in happen together so the inspector sees one coordinated visit instead of three. Most garages have no plumbing at all, so we’re trenching the slab for the bathroom drain and tying into the main house stack. Electrical is usually a subpanel or a dedicated circuit run from the main service. HVAC means either extending the house system or a dedicated mini-split. This is the messiest stretch and the one most likely to add days if the existing service panel is already full.
Stage 4: Insulation, drywall, and finishes (3 to 4 weeks)
Closed-cell spray foam goes in the walls and ceiling, partly for the energy code and partly because an uninsulated garage ceiling makes the space unusable in July. Then drywall, tape, texture, paint, flooring, cabinetry, and fixtures. You’ll lock in finish selections in week one of this stage: flooring, cabinet fronts, countertop, and bathroom tile. Late changes here are the single most common reason a conversion runs over budget.
Stage 5: Trim-out, final inspection, and certificate of occupancy (2 to 3 weeks)
The last stretch is setting the fixtures, the mini-split startup, the smoke and CO detectors, and the final inspection that converts the space from “garage” to “accessory dwelling unit” on paper. That certificate matters. Without it, the space is not a legal ADU, and it can create problems at resale or with your insurer.
Styles & brands we work with
- Kitchen remodeling
- Bathroom remodeling
- Home additions & ADU
- Roofing
- Windows & doors
- Driveway & pavers
- Fence
The Choices You’ll Actually Make on a Garage Conversion ADU
- Overhead door replacement vs. infill wall: Most homeowners close the opening with a framed wall and a single impact-rated entry door plus a window. That’s cheaper and gives better insulation. Keeping a roll-up door for storage means you give up the wall and lose usable living space. The infill route is what we recommend almost every time.
- Impact-rated glazing vs. standard: A garage conversion needs impact-rated windows and doors to pass wind-load review, not just for insurance. We use Andersen and Pella impact assemblies where the opening is exposed. The trade-off is cost and lead time; the alternative is shutter-dependent glazing, which most Three Lakes HOAs won’t approve anymore.
- Full kitchen vs. kitchenette: A full kitchen adds range, full-size refrigerator, dishwasher, and dedicated circuits. A kitchenette with a sink, cooktop, and under-counter fridge saves roughly $8,000 – $15,000 and keeps the layout simpler. If you plan to rent the unit, a full kitchen rents higher.
- Slab-on-grade bathroom vs. raised floor: Trenching into the existing slab is the standard approach. A raised platform avoids the concrete work but costs you headroom and feels odd in a small unit.
- Dedicated mini-split vs. extending the house system: A mini-split gives the tenant their own thermostat and is easier to permit. Extending the main system is cheaper upfront only if the existing unit is oversized.
- Flooring: Luxury vinyl plank handles humidity and quick cleaning better than carpet in a unit that might see a renter. Porcelain tile is the durable choice, and it’s roughly $2 – $4 more per square foot installed.
What a Garage Conversion ADU Costs in Three Lakes, FL

Plan on $45,000 – $130,000 for the conversion itself. The low end is a studio with a kitchenette, no structural surprises, and an existing service panel with room to spare. The high end is a one-bedroom with a full kitchen, new impact glazing throughout, a bathroom requiring slab trenching, and structural reinforcement at the roof-to-wall connection.
Five things push the number:
- Square footage: A one-car garage (about 250 sq ft) sits at the bottom; a two-car (400+ sq ft) adds framing, drywall, flooring, and finish cost across the whole envelope.
- Existing condition: Original single-pane openings, a full electrical panel, or a slab with cracks and moisture all force work that wasn’t in the first bid.
- Moving plumbing and electrical: A bathroom on the far side of the garage from the house stack can add several thousand dollars in trenching and re-routing.
- Finish grade: Builder-grade cabinets and LVP vs. KraftMaid cabinetry and stone counters is a $15,000 – $25,000 swing on its own.
- Permit scope: If the project touches the roof structure or the main electrical service, the permit set grows.
A written estimate from us lists every line item: framing, rough-in trades, insulation, finishes, the impact door and window package, permit fees, and the final inspection. It does not include furniture, appliances you buy yourself, or landscaping once the unit is done. Upfront pricing, no surprises: the number you see is the number you pay.
See the difference
Before
After
Before
After
Before
AfterWhat Three Lakes Homes Specifically Do to This Job
Three Lakes (ZIP 33186) is a planned community built mostly in the 1980s and 1990s around a chain of man-made lakes, and the housing stock changes how a garage conversion goes. Most of what we touch here is concrete block construction with stucco walls and concrete tile or flat built-up roofs. That CBS construction is a real advantage for a conversion: the walls are solid and load-bearing where it counts, and the mass keeps the unit quieter than a wood-frame addition would.
What’s less helpful is the era. A lot of these garages still have original single-pane garage doors and windows, and a conversion that keeps any of them fails wind-load review. We also run into original polybutylene plumbing on these homes, and if the garage tie-in hits it, we replace the run rather than connect new work to failing pipe. Strict HOA rules in the community mean exterior changes to the door and window configuration usually need architectural review before we pull the permit, and that review adds one to two weeks to the front end. Near-lake lots can also trigger drainage and easement considerations if the conversion changes site grading at all.
We cover the whole of Three Lakes for this work, and homeowners often pair the conversion with a new driveway surface once the garage stops being a garage. If that’s on your list, Concrete Driveways & Concrete Work in Three Lakes is the natural companion, and for a longer paved run, Asphalt Driveways & Resurfacing in Three Lakes. Bigger picture: a garage conversion is often the first phase of a wider plan, and you can see the full scope on our Home Additions & ADU in Three Lakes page.
Serving Three Lakes, FL – Our Local Coverage Area
We serve Three Lakes and nearby communities. Use the map below to see the area we cover. If you’re nearby, we can almost certainly help.
Frequently Asked – Garage Conversion ADU in Three Lakes

Most garage conversion ADU projects in Three Lakes run 4 to 7 months from permit submittal to certificate of occupancy. The build itself is about 8 to 12 weeks; the rest is the permit set, HOA architectural review, and the inspection chain. Call (844) 834-8961 for an exact timeline on your garage.
Yes. A garage conversion is an occupancy change, so it requires a permit and a final inspection to make the unit legal. Working without one can cost you the space at resale and create insurance problems. We pull the permits and carry the project through every inspection.
Sometimes, if the bathroom can sit close to the existing house plumbing stack and the garage door opening is already framed out. Most jobs need at least a trench in the slab and a new infill wall where the overhead door was. We confirm both on the first visit. Call (844) 834-8961 for a free on-site estimate.
The range is $45,000 – $130,000, with the low end being a studio with a kitchenette and the high end a one-bedroom with a full kitchen and new impact glazing. Call (844) 834-8961 for an exact quote. Estimates are free.
Every garage conversion ADU we build is covered by our 730-Day Done Right Promise: if it’s not done right, we make it right. That’s one of the longest workmanship guarantees in the residential construction space, and it applies to the framing, finishes, and trades on your conversion.
Get a Free On-Site Estimate for Your Garage Conversion ADU in Three Lakes
We’ll walk your garage, measure the slab and ceiling height, check the door opening and the existing panel, and hand you a written line-item estimate with the full scope and the permit path. Financing is available at 0% for 18 months, and projects over $10,000 get $1,000 off. Our home additions & adu service runs the same crew from foundation to finish line. Call (844) 834-8961 to schedule your free estimate in Three Lakes.
Written by the team at Groundwork Construction Co.