New Detached ADU in Kendale Lakes, FL: What It Takes
A new detached ADU in Kendale Lakes runs $45,000 to $130,000 for most homeowners, and a standalone unit usually takes four to seven months from first permit submittal to final inspection. That window covers Miami-Dade permitting, poured foundation, CBS block walls, roof, utilities, and finishes. Call (844) 834-8961 to schedule your free estimate. We’ll walk your lot, check setbacks against your zoning, and put real numbers on paper before anyone signs anything.
How We Build a New Detached ADU in Kendale Lakes, Step by Step

Detached means the unit stands on its own foundation with its own roof, utilities, and address. That changes the sequence compared to an interior conversion. Here’s what actually happens.
- 1
Stage 1: Site visit and feasibility, week one. We measure the lot, mark setbacks, and confirm where the ADU can legally sit. In Kendale Lakes the lots are small, so footprint placement drives everything. You decide the approximate size and whether it’s a studio, one-bedroom, or two-bedroom layout. We also check your HOA’s architectural guidelines at this stage, because a detached structure almost always triggers review.
- 2
Stage 2: Design and permit submittal, weeks two through six. Drawings go to Miami-Dade County for plan review. This is the longest stretch with the least visible progress. HVHZ wind-loading calculations, roof-to-wall tie-downs, and opening protection all get scrutinized here. You sign off on the floor plan and exterior elevation – and if your community has an architectural review board, that packet goes out in parallel, which can add two to four weeks.
- 3
Stage 3: Site prep and foundation, weeks six through nine. Clearing, grading, and utility trenching happen first, then the slab or stem-wall foundation gets poured and inspected before anything goes vertical. You don’t need to decide anything here unless the soil report turns up something unexpected.
- 4
Stage 4: Block, roof, and rough-ins, weeks nine through eighteen. CBS walls go up, the roof frame and decking go on, then plumbing, electrical, and mechanical rough-ins get inspected. This is the busiest stretch. You pick finishes now: flooring, cabinets, fixtures, and anything on the kitchen link below.
- 5
Stage 5: Finishes and final inspection, weeks eighteen through twenty-eight. Drywall, paint, trim, countertops, and final utility connections. The county does its last walkthrough and issues the certificate of occupancy. You walk the unit with us before we hand over the keys.
If the ADU is part of a full Home Additions & ADU in Kendale Lakes plan that touches the main house, the two scopes can run together – but the detached unit keeps its own permit and its own inspection schedule.
Styles & brands we work with
- Kitchen remodeling
- Bathroom remodeling
- Home additions & ADU
- Roofing
- Windows & doors
- Driveway & pavers
- Fence
The Choices You’ll Actually Make on a Detached ADU
Most of the big decisions are made before the first block is laid. Here’s what moves the price and the outcome, and the honest trade-off on each.
- Size and bedroom count. A 400 sq ft studio is the cheapest and easiest to permit. A 700 – 900 sq ft one-bedroom with a full kitchen costs more but rents or houses family far better. Two-bedroom units push you toward the top of the range.
- Wall system. CBS concrete block with stucco matches the surrounding Kendale Lakes homes and handles HVHZ wind loading well. Frame with impact-rated sheathing is faster but needs careful waterproofing. We recommend block here for durability and resale.
- Roof. Low-pitch tile matches the neighborhood look; a standing-seam metal roof lasts longer and shrugs off wind-driven rain. Both meet Miami-Dade code; the choice is cost versus longevity.
- Kitchen and bath finishes. This is where budgets flex most. A modest kitchen with Kohler fixtures and a Caesarstone counter sits near the low end; upgraded cabinetry and stone push higher. Pick the finishes that survive humidity – quartz over porous natural stone.
- HVAC and water heater. A dedicated mini-split system keeps the ADU independent from the main house. A heat-pump water heater saves on the long-run electric bill.
- Impact openings. Required for HVHZ compliance and worth every dollar – they cut insurance premiums and eliminate shutter-hanging during storm prep.
What a New Detached ADU Costs in Kendale Lakes, FL

Expect $45,000 to $130,000 for a detached ADU here, with most single-bedroom units landing in the middle of that curve. Here’s how the line items break down.
| Line item | Typical range |
|---|---|
| Design and permit fees | $4,000 – $12,000 |
| Site prep and foundation | $6,000 – $16,000 |
| CBS walls and roof | $18,000 – $45,000 |
| Plumbing, electrical, HVAC | $9,000 – $22,000 |
| Interior finishes and fixtures | $8,000 – $35,000 |
Five things push a job toward the high end: a larger footprint, moving utility connections a long distance from the main house, upgraded finishes, an HOA review board that requires design revisions, and any surprise in the soil or existing drainage on a built-out lot. A written estimate from us lists what’s included – permits, inspections, and the workmanship warranty – and what isn’t, like landscaping repair after trenching. If your main house needs its own kitchen work at the same time, homeowners often pair this with a kitchen remodel or a bathroom refresh in the main home while we’re already on site. Financing is available at 0% for 18 months, and projects over $10,000 take $1,000 off.
See the difference
Before
After
Before
After
Before
AfterWhat Kendale Lakes Lots Do to This Job
Kendale Lakes is a large, fully built-out 1970s – 80s planned subdivision in unincorporated Miami-Dade west of the Turnpike, so there are no vacant lots to build on. A detached ADU here means adding a structure to a small, already-developed parcel next to a concrete-block tract home built to pre-Andrew or early-Andrew standards. That reality shapes the job: setbacks are tight, drainage has to be routed carefully so a new slab doesn’t flood a neighbor’s yard, and the unit itself must meet current Miami-Dade High Velocity Hurricane Zone wind-loading, tie-down, and continuous flashing standards – not the standard the main house was built to. HOA architectural review in the planned sections is a real gate: roof style, wall color, fence height, and even landscaping have to match the community. We prepare the ARB packet alongside the county submittal so both move together. Along Kendall Drive and the residential streets feeding off it, we’ve seen plenty of original drainage that needs adjusting before a new pad goes down. If the ADU needs a widened approach or a new parking pad, homeowners often pair this with Concrete Driveways & Concrete Work in Kendale Lakes or Paver Driveways in Kendale Lakes. We handle all of it through our Home Additions & ADU service and cover every job across Kendale Lakes.
Serving Kendale Lakes, FL – Our Local Coverage Area
We serve Kendale Lakes and nearby communities. Use the map below to see the area we cover. If you’re nearby, we can almost certainly help.
Frequently Asked: New Detached ADU in Kendale Lakes

A new detached ADU takes four to seven months from permit submittal to certificate of occupancy, with plan review and HOA architectural review often adding four to six weeks on top. Call (844) 834-8961 for a schedule built around your lot.
Yes. A detached ADU in Kendale Lakes always needs a Miami-Dade County building permit – it’s a new structure with its own foundation, roof, and utility tie-ins, and it must meet HVHZ wind-loading standards. Your HOA may require architectural review before work starts. We handle the submittal paperwork for both.
Yes, in most cases a detached ADU runs on its own foundation with its own meter, mini-split HVAC, and water heater, so nothing inside the main house gets opened up. The only tie-in is the utility trench connecting to the service. We confirm soil, setbacks, and drainage at the site visit.
A new detached ADU in Kendale Lakes costs $45,000 to $130,000, depending on size, finish grade, and how far utilities have to run. Your written estimate lists each line item up front. Call (844) 834-8961 and we’ll price your actual lot – estimates are free.
Every build carries our 730-Day Done Right Promise – if it’s not done right, we make it right. That’s one of the longest workmanship guarantees in the residential construction space, and it’s in writing.
Get a Free Estimate for a New Detached ADU in Kendale Lakes
Call (844) 834-8961 for a free on-site estimate on a New Detached ADU in Kendale Lakes. A live person answers around the clock, and we’ll set a time that fits your schedule. We’ll walk the lot, confirm setbacks and HOA requirements, and hand you a written, line-item estimate with the 730-Day Done Right Promise attached. No pressure, no vague range – just real numbers for your property.