New Detached ADU in Three Lakes, FL: What It Takes and What It Costs
A new detached ADU in Three Lakes is a freestanding, self-contained second home built on your lot – its own foundation, roof, kitchen, bath, sleeping area and utility service – and it usually runs $90,000 to $220,000 depending on size, finish level and site conditions. Most builds here take 5 to 8 months from permit submittal to certificate of occupancy, longer than most homeowners expect because Miami-Dade inspections stack up. Call (844) 834-8961 to schedule a free on-site estimate and we’ll walk your lot and talk through what’s realistic on your property.
How a Detached ADU Gets Built, Stage by Stage

Every build follows the same spine, and knowing it keeps you from being surprised halfway through. Here’s the sequence we run on a typical Three Lakes detached ADU.
Stage 1: Site walk and feasibility (days 1-5)
We measure the lot, confirm setbacks and your HOA restrictions, and check where the water, sewer and electrical actually come in. On 1980s-1990s Three Lakes lots, this is where we find out whether a mature oak or ficus hedge is going where you wanted the ADU, and whether the utility tap is on the near or far side of the house. This is the stage where you decide the footprint and where the structure sits. Nothing gets designed around a number we haven’t confirmed.
Stage 2: Design and permit submission (weeks 2-8)
Working drawings, structural engineering and energy calcs go to your municipality in the 33186 corridor. Your decision here: window and door spec, roof form, and whether the ADU is impact-rated throughout (it should be). Miami-Dade review typically takes 4 to 8 weeks, and lake-adjacent lots can add time because drainage and easement review gets pulled in. We pull the permits and take the inspections – you don’t touch paperwork.
Stage 3: Site prep and foundation (weeks 1-3 of construction)
Clearing, grading, and forming for the slab or stem wall foundation. This is where the high water table tells us what we’re actually building on – more on that below. You decide: whether the ADU gets a slab-on-grade (usual, cheaper) or a raised stem wall foundation (better drainage margin, higher cost).
Stage 4: Structure, skin and systems (weeks 4-12)
Concrete block walls go up and get tied into a code-compliant roof structure. Roof-to-wall connections are wind-rated for South Florida. Rough-in for plumbing, electrical and HVAC happens inside the walls before drywall, and you’ll be asked to lock your fixture and finish choices by this point or risk order delays. Stucco exterior to match the main house, tile or impact-rated roofing.
Stage 5: Finishes, inspection and handover (weeks 13-20)
Drywall, paint, flooring, cabinets, countertops, fixtures and final systems. We run the inspection sequence – electrical, plumbing, building, final – and a certificate of occupancy triggers. Then we walk it with you, punch list in hand. The whole job sits under our 730-Day Done Right Promise; if it’s not done right, we make it right.
Styles & brands we work with
- Kitchen remodeling
- Bathroom remodeling
- Home additions & ADU
- Roofing
- Windows & doors
- Driveway & pavers
- Fence
The Options You’ll Actually Choose Between on a Detached ADU
- Footprint and size – a 400 to 600 sq ft one-bedroom ADU is the sweet spot for most Three Lakes lots: enough to rent or house a family member without crowding the yard or eating your pool area. A 700 to 900 sq ft two-bedroom adds real rental income but also adds cost across every line. Decide your use case first: caregiver housing, rental unit, or guest / office space.
- Foundation type – slab-on-grade is the standard and the cheaper route. A raised stem wall foundation costs more but gives you breathing room against the water table that can rise in a west Kendall wet season. We test and tell you which the lot actually calls for.
- Roof form – a hip-roofed or gabled tile roof matches the 1980s-1990s CBS housing stock here and reads as a real addition to the property. A low-slope or flat built-up roof costs less and matches homes that already run flat roofs, but it ages faster in the South Florida sun and needs more vigilant drainage.
- Windows and doors – impact-rated windows and doors are non-negotiable for a new structure in Miami-Dade, and it’s also the difference between clear weather and a boarded-up ADU every hurricane season. Go impact-rated throughout; brands like Andersen and Pella are in our catalog, and we won’t install anything that doesn’t pass wind-load on paper.
- Exterior finish – stucco to match the main house is standard. James Hardie siding is an option where the main structure already runs it and you want the ADU to read as a distinct design rather than a clone.
- Utility service – you choose between a sub-panel off the main house (cheaper, cleaner) or a separate meter (cleaner for rental accounting, more permit and utility coordination).
- Kitchen and bath level – a rental-grade kitchen (KraftMaid or comparable cabinet line, laminate or entry quartz, basic appliances) versus a move-in-permanent family spec (Cambria quartz, better appliances, tile elsewhere). This one choice swings the total more than most people realize.
- Flooring – luxury vinyl plank is durable and rental-proof; porcelain tile handles moisture and heat better and looks more upscale; carpet only for a bedroom, if at all in this climate.
What a New Detached ADU Costs in Three Lakes, FL

The range for a new detached ADU in Three Lakes is $90,000 to $220,000, with most builds landing in the $120,000 to $170,000 band. That window is driven by five real variables, not marketing jargon:
- Size – moving from a 400 sq ft studio to a 900 sq ft two-bedroom roughly doubles the structural cost before finishes. Size is the biggest lever you control.
- Site condition – a flat, clear lot with utilities already on the near side is the low end. A lot that needs fill, grading, tree removal, or a utility tap run a long distance pushes toward the high end. Lakefront properties with drainage easees and seawall-proximity issues sit at the top of that swing.
- Permit scope – a clean, straightforward submittal on a standard lot costs less in time and review than a lake-adjacent lot that pulls in drainage easement review. Both get fully permitted and inspected – one just takes more coordination.
- Finish level – rental-grade versus family-permanent finishes can move the number by tens of thousands of dollars on the same footprint. We’ll show you both sides in writing.
- Systems and service – a separate meter, a higher efficiency HVAC, or an upgraded electrical service all add to the number.
Every estimate we write is a line-item, fixed-price document. What you see is what you pay, and there are no change orders from us quietly adding to the bottom line. Financing is available at 0% for 18 months, and projects over $10,000 get $1,000 off. If you’re also laying a new driveway or pad to the ADU, homeowners often pair this with Concrete Driveways & Concrete Work in Three Lakes or Paver Driveways in Three Lakes – we’ll quote it all together so nothing gets double-charged.
See the difference
Before
After
Before
After
Before
AfterWhat Three Lakes Homes Specifically Do to a Detached ADU Build
Three Lakes was built up mostly through the 1980s and 1990s as a planned community wrapped around a chain of man-made lakes, and the housing stock – CBS block walls, stucco, concrete tile or flat built-up roofs, screened lanais – shapes how a new detached ADU has to sit next to it. The lots aren’t huge, the setbacks are tight, and HOA rules for accessory structures can be finicky, so where we place the structure and how tall it rises gets scrutinized earlier than a lot of homeowners expect. The high water table and the frequency of heavy downpours mean foundation and drainage decisions aren’t theoretical here; a slab that’s fine on paper can struggle after a late-summer storm if grading isn’t right. Some older homes still carry original polybutylene plumbing or single-pane windows that won’t pass current wind-load or energy standards on a new-construction review, and on lake-adjacent lots drainage easement and seawall proximity can pull extra layers into the permit review. We work these details into the estimate up front so there’s no surprise after we’ve broken ground. Learn more about the full scope on our Home Additions & ADU service page, or read up on Home Additions & ADU in Three Lakes if the ADU is part of a broader plan for the property.
Serving Three Lakes, FL – Our Local Coverage Area
We serve Three Lakes and nearby communities. Use the map below to see the area we cover. If you’re nearby, we can almost certainly help.
Frequently Asked – New Detached ADU in Three Lakes

Most builds run 5 to 8 months from permit submittal to certificate of occupancy, with the permit review itself typically 4 to 8 weeks in this part of Miami-Dade. Construction is roughly 16 to 20 weeks after permits clear, depending on weather during hurricane season. Call (844) 834-8961 for a timeline based on your specific lot.
Yes – a new detached ADU requires full building permits and a certificate of occupancy, without exception. It touches zoning, setbacks, utility connections, structural, electrical, plumbing, and often HOA review on top. We pull every required permit and pass every required inspection as part of the job.
In most cases, yes – the ADU runs on its own plumbing and electrical service, tied to the main house only at the utility tap. If a sub-panel off the main house is the choice, we may need to upgrade the main electrical service; if a separate meter is chosen, we coordinate with the utility. Either way, we tell you before ground is broken.
The range is $90,000 to $220,000, with most builds landing $120,000 to $170,000 for a 400 to 700 sq ft one- or two-bedroom. The number moves on size, site condition, finish level and utility scope. Call (844) 834-8961 for an exact quote – estimates are free, line-item, and fixed-price.
Every ADU we build carries the 730-Day Done Right Promise – if something isn’t right within two years, we come back and make it right, at no cost to you. Brand partners like Andersen, KraftMaid, James Hardie and others carry their own manufacturer warranties on top. That’s among the longest workmanship guarantees in the residential construction space, and it’s in writing.
Get a Free On-Site Estimate for Your Detached ADU in Three Lakes
The call starts with real questions, not a sales pitch. We’ll ask how you plan to use the ADU, look at your lot, confirm setbacks and HOA constraints, and come back with a written, line-item, fixed-price estimate inside the $90,000 to $220,000 range with a realistic timeline attached. A live person answers every call, 24 hours a day. Call (844) 834-8961 to schedule your free estimate and design consult in Three Lakes – we’ll take it from feasibility through the final walkthrough, backed by our 730-Day Done Right Promise.