What a New Detached ADU in Kendall, FL Actually Involves
A new detached ADU in Kendall is a fully separate second dwelling built on your lot, usually 600 to 1,000 square feet, with its own entrance, kitchenette, bathroom and utility connections. Plan on 6 to 9 months from permit submission to final inspection, and budget $90,000 – $220,000 depending on size and finish level. Call (844) 834-8961 for a free on-site estimate and we’ll walk your lot and give you a written line-item number.
How We Build a Detached ADU, Stage by Stage
Every ADU we build follows the same sequence. Here’s what actually happens, week by week, and what you have to decide along the way.
- Stage 1 – Site walk and feasibility (week 1). We measure setbacks, check where the sewer lateral and electrical service enter the house, and confirm what your lot can legally hold under Miami-Dade zoning. You decide footprint and placement at the end of this stage. This is the step where we find the 1990s-era enclosed patios and converted garages that many Kendall homes carry, because anything unpermitted has to be brought into compliance before a new ADU gets approved.
- Stage 2 – Design, engineering and permit (weeks 2 through 8, sometimes 10). Stamped drawings go to Miami-Dade for building, zoning and product approval review. Because Kendall sits in the High-Velocity Hurricane Zone, every window, door, roof system and tie-down gets checked against product approval numbers. You choose the exterior finish and opening protection here, since those specs go into the permit set. You do not pick interior finishes yet.
- Stage 3 – Site prep and foundation (weeks 9 through 13). We clear the footprint, trench for water, sewer and power, and pour the slab or stem-wall foundation. Inspections happen at underground plumbing and at slab. You don’t need to make decisions during this window, which is a good time to finalize interior selections.
- Stage 4 – Shell, dry-in and rough trades (weeks 14 through 22). Concrete block walls go up, the roof ties in, and rough electrical, plumbing and mechanical get inspected. We schedule around rainy season where we can, because a stalled slab sets the whole job back.
- Stage 5 – Finish-out and final inspections (weeks 23 through 30). Insulation, drywall, cabinets, tile, fixtures, paint and final inspection. You’ll sign off on a walkthrough punch list before we call for the certificate of occupancy.
Styles & brands we work with
- Kitchen remodeling
- Bathroom remodeling
- Home additions & ADU
- Roofing
- Windows & doors
- Driveway & pavers
- Fence
The Options You’ll Choose Between
Most of the money decisions on a detached ADU come down to four choices. Each has a real trade-off, and we’ll price all of them in writing so you can see the difference before you commit.
- Attached-carport style versus slab-on-grade foundation. Slab is the cheaper and simpler build on Kendall’s flat lots. A raised stem-wall foundation costs more but helps with drainage on lots that pool water after a hard summer storm.
- Concrete block versus wood-frame construction. Block is the standard for Kendall and what most lenders and appraisers expect. It resists moisture and wind better. Frame is faster and cheaper per square foot but harder to insure and less common in this market.
- Impact-rated openings versus shutters. Impact windows and doors cost more up front and simplify your insurance picture. Shutters are cheaper upfront but add a pre-storm chore every season, and you’ll still need product approval for whatever you choose.
- Kitchenette versus full kitchen. A kitchenette keeps the ADU permit simpler and cheaper. A full kitchen with a range and vent hood costs more and needs more mechanical work, but it lets the unit function as a true rental.
Exterior finish is the fifth call – stucco is the near-universal choice here and holds up well in the sun and rain. Where a fence or privacy screen matters on the lot line, homeowners often pair this with Paver Driveways in Kendall or a privacy fence in Barrette or Master Halco panels for the yard side.
What a New Detached ADU Costs in Kendall, FL

Detached ADU construction in Kendall runs $90,000 – $220,000, and the number moves most on size, site conditions, opening protection, finish level and permit scope. Here’s how the range breaks down against the wider work it belongs to.
| Item | Kendall range |
|---|---|
| Detached ADU, full build | $90,000 – $220,000 |
| Home addition (for comparison) | $45,000 – $130,000 |
| Garage conversion (alternate route) | $30,000 – $80,000 |
The low end of that ADU range buys a compact 500 to 600 square foot studio with a kitchenette and standard finishes. The high end is a 900 to 1,000 square foot one-bedroom with a full kitchen, premium tile, custom cabinetry and impact-rated everything. What pushes a job toward the top: extra square footage, relocating or upgrading the electrical service, running a long sewer lateral, unpermitted prior work that has to be corrected, and upgraded cabinetry or counters.
A written estimate from us includes design coordination, permit fees, foundation, framing, roofing, all mechanical rough and finish, and the final inspection. It does not include landscaping restoration, furniture, or appliances you buy yourself. The number you see is the number you pay, and the whole job is backed by our 730-Day Done Right Promise. Call (844) 834-8961 for an exact quote – estimates are free.
See the difference
Before
After
Before
After
Before
AfterWhat Kendall Homes Specifically Do to This Job
Kendall’s housing stock changes how a detached ADU gets built here. Most of the lots we work on sit in the 1970s to 1990s subdivisions – Kendale Lakes, The Hammocks and the blocks around Kendall Drive – where the main house is concrete block with a low-slope or flat roof. That matters because on many of these properties, especially anything built before 1994, there’s an enclosed patio or converted garage that was never permitted. It surfaces the moment you pull an ADU permit, and it has to be brought into compliance under Miami-Dade product approval rules before your new unit gets the green light. We plan for that correction in the schedule and the budget. The other local factor is weather: Kendall’s HVHZ wind-load and moisture standards mean every opening and roof assembly on the ADU gets scrutinized at plan review, and we schedule concrete and roofing around the summer rainy season so a stalled pour doesn’t cost you weeks. If you’re comparing this to a broader remodel, our Home Additions & ADU in Kendall page covers the wider scope, and the full Home Additions & ADU service hub shows how an ADU fits alongside a main-house project. We build across Kendall and the surrounding neighborhoods.
Serving Kendall, FL – Our Local Coverage Area
We serve Kendall and nearby communities. Use the map below to see the area we cover. If you’re nearby, we can almost certainly help.
Frequently Asked – New Detached ADU in Kendall

Expect 6 to 9 months from permit submission to certificate of occupancy. The permit review alone takes 6 to 10 weeks in Miami-Dade, and rainy-season delays can add weeks to the foundation and roof stages. Call (844) 834-8961 and we’ll give you a schedule for your specific lot.
Yes. A detached ADU requires building, zoning and product approval permits from Miami-Dade, and every opening and roof assembly has to meet HVHZ standards. We pull the permits and manage the inspections as part of the job. Call (844) 834-8961 to start the conversation.
Often, yes. We run new service and utilities directly to the ADU so the main house stays untouched. The exception is when the existing panel or sewer lateral can’t carry the added load, and we’ll tell you that at the site walk, not mid-build.
Detached ADU construction runs $90,000 – $220,000 depending on size, finish level and site conditions. Call (844) 834-8961 for a free on-site estimate – our written quote is line-item and fixed.
Every ADU we build is covered by our 730-Day Done Right Promise. If it’s not done right, we make it right, and the guarantee runs one of the longest workmanship terms in the residential construction space.
Get a Free Estimate for Your New Detached ADU in Kendall
Call (844) 834-8961 to schedule a free on-site estimate for your new detached ADU in Kendall. A live person answers around the clock, and we’ll walk your lot, confirm setbacks and utility routes, and give you a written line-item quote with a fixed price. No surprise numbers, no pressure. Financing at 0% for 18 months is available, and projects over $10,000 get $1,000 off.
Written by the team at Groundwork Construction Co. of Kendale Lakes.